Red-Amber-Green warning thresholds
Your Editor To-Do List displays red-amber-green warnings next to the different folders to prompt you to take action. The different thresholds for this colour coding are shown below.
Stage | Amber alert - needs attention | Red alert - late |
---|---|---|
New and revised submissions | 10 days since initial date submitted | 20 days since initial date submitted |
Transferred Submissions | 10 days since initial date submitted | 20 days since initial date submitted |
Submissions Sent Back to Author for Approval | 10 days since last status update | 20 days since last status update |
New Assignments | 10 days since last status update | 20 days since last status update |
Submissions with Required Reviews Complete | 10 days since the most recent review was submitted | 20 days since the most recent review was submitted |
Submissions Requiring Additional Reviewers | 10 days since initial date submitted | 20 days since initial date submitted |
Submissions with One or More Late Reviews | 10 days since the first review became late | 20 days since the first review became late |
Reviewers Invited - No Response | 10 days since the first reviewer that hasn't responded was invited | 20 days since the first reviewer that hasn't responded was invited |
Submissions Under Review | 10 days since the first reviewer was invited | 20 days since the first reviewer was invited |
Group by Editors I Assigned | 10 days since you assigned submission to another editor | 20 days since you assigned submission to another editor |
Group by Editor with Current Responsibility | 10 days since current editor was assigned | 20 days since current editor was assigned |
All Submissions with Editor's Decision | 10 days since the last decision was made | 20 days since the last decision was made |
My Assignments with Decision | 10 days since the last decision was made | 20 days since the last decision was made |