2022Q2 RevMan Web development progress
Sprint plan
Est start date | Epic/backlog item |
---|---|
2022-04-18 | (3 week sprint) Import study data: Export to generate test data, paste study characteristics, import from file |
2022-05-09 | Paste study characteristics, Import study data from file |
2022-05-23 | Complete Import study data from file, Bugs |
2022-06-06 | Import tabular study data, ,Move to Angular |
2022-06-20 | Import tabular study data, DTA scoping, Import DTA reviews from RM5, Create empty DTA review with common functionality |
2022-07-04 | Project management features in RevMan, Limited capacity due to summer holidays |
2022-07-18 | Project management features in RevMan, Limited capacity due to summer holidays |
2022-08-01 | Project management features in RevMan |
Agenda Sprint demo
What did we complete in the sprint?
- Short summary
- Demo of new functionality
- Feedback
- Summarize comments from demo
- Update on comments from previous demo
How are we progressing towards our quarterly targets?
Adoption and activity in RevMan Web
Sprint started
Completed:
Story | Objective/Epic | Release | Demo |
---|---|---|---|
Show lifecycle status for projects in status panel | Project management | 11/8 | 12/8 |
Show, add, edit and remove tasks | Project management | 11/8 | 12/8 |
Assign and mark milestones and tasks as complete | Project management | 11/8 | 12/8 |
Show, set and edit due dates | Project management | 11/8 | 12/8 |
Reopen milestones and tasks | Project management | 11/8 | 12/8 |
Improvements to import validation | Project management | 11/8 | 12/8 |
Shared author footnotes | 11/8 | - |
Feedback:
- Porto lifecycle management:
- "Complete" life cycle status not clear what it means - suggestion: "Inactive"
- Distinguish between withdrawn and published in life cycle management (they are very different)
- How would we categorize statuses for living systematic reviews in Cochrane?
- Ability to easily find review in any life cycle status
- Search for review
- Tab with all reviews
- Project management
- Legend for the colors?
- Filter by status
- Filter by tasks assigned to person
- Review color shades for accessibility (e.g. color blindness)
- History for changes to project management? To undo actions/to know what happened in a project: you could compare with Porto template
- Ability to restrict authors from adding/deleting tasks (e.g. introduce project manager role)
- Is the term "Project" ideal? Maybe not but it needs to account for very different types of work related to a review. Consider using "project" term in UI in fewer places.
Activity panel last 30 days
Reviews with advanced features (only use RevMan Web)
- In total: 297 (+3)
- GRADEPro integration: 200 (+2)
- RoB 2: 161 (+2)
- Study-centric data: 11 (+0)
Overall activity RevMan Web vs. RevMan 5 (2 years)
Sprint started
Completed:
Story | Objective/Epic | Release | Demo |
---|---|---|---|
Other work completed:
- 3 Project management tickets in code review/testing stage
- 2 E2E test
- 2 bug fix
Activity panel last 30 days
Reviews with advanced features (only use RevMan Web)
- In total: 294 (+1)
- GRADEPro integration: 198 (+2)
- RoB 2: 159 (+2)
- Study-centric data: 11 (+0)
Overall activity RevMan Web vs. RevMan 5 (2 years)
Sprint started
Completed:
Story | Objective/Epic | Release | Demo |
---|---|---|---|
Import data from files with tabular data | Retire RevMan 5/ Improve transfer of data into RevMan Web | 14/7 | Demoed 1/7 |
Other work completed:
- Nightly run of E2E tests on AWS
- 1 E2E test
- 1 bug fix
Activity panel last 30 days
Reviews with advanced features (only use RevMan Web)
- In total: 293 (+3)
- GRADEPro integration: 196 (+1)
- RoB 2: 157 (+3)
- Study-centric data: 11 (+0)
Overall activity RevMan Web vs. RevMan 5 (2 years)
Sprint started
Completed:
Story | Objective/Epic | Release | Demo |
---|---|---|---|
Import data from files with tabular data | Retire RevMan 5/ Improve transfer of data into RevMan Web | TBD | Yes |
View versions where study-centric analyses are incomplete | 30/6 | Yes | |
For reviews with Risk of bias 2 enabled you cannot add Risk of bias summary and risk of bias graph | 30/6 | Yes | |
Allow GRADEPro integration to be disabled | 30/6 | Yes | |
Check if user wants to clear calculator input | 30/6 | No |
Other work completed:
- Progress on moving to Angular
- Convert all non-model services to Angular
- Make CONFIG a constant
Activity panel last 30 days
Reviews with advanced features (only use RevMan Web)
- In total: 290 (+9)
- GRADEPro integration: 195 (+1)
- RoB 2: 154 (+8)
- Study-centric data: 11 (+1)
Overall activity RevMan Web vs. RevMan 5 (2 years)
Sprint started
Completed:
Story | Objective/Epic | Release | Demo |
---|---|---|---|
Calculator for arm-level continuous data for study-centric results | Retire RevMan 5/ Improve transfer of data into RevMan Web | 16/6 2022 | Yes |
Restrict users from adding review level concepts with exactly the same name | Retire RevMan 5/ Improve transfer of data into RevMan Web | 16/6 2022 | Yes |
Update PICO section to include risk of bias and study characteristic setup | Retire RevMan 5/ Improve transfer of data into RevMan Web | 16/6 2022 | Yes |
Handle invalid analysis data more appropriately when pasting | Retire RevMan 5/ Improve transfer of data into RevMan Web | 16/6 2022 | Yes |
On export of study data, if a risk of bias list is empty, leave out risk of bias completely | Retire RevMan 5/ Improve transfer of data into RevMan Web | 16/6 2022 | Yes |
Other work completed:
- Migration of ReviewDB to AWS completed
- 5 End-2-End automatic tests
- 2 bugs fixed
- Convert model services to Angular
Activity panel last 30 days
Reviews with advanced features (only use RevMan Web)
- In total: 281 (+20)
- GRADEPro integration: 194 (+8)
- RoB 2: 146 (+10)
- Study-centric data: 10 (+2)
Overall activity RevMan Web vs. RevMan 5 (2 years)
Sprint started
Completed:
Story | Objective/Epic | Release | Demo |
---|---|---|---|
Import study data from file | Improve transfer of data into RMW | Yes | No |
Update text in confirmation dialog for Edit and Update SoF | - | No |
Other work completed:
- End-2-End automatic tests
- 12 bugs fixed
Activity panel last 30 days
Reviews with advanced features (only use RevMan Web)
- In total: 261 (+0)
- GRADEPro integration: 182 (+0)
- RoB 2: 136 (+0)
- Study-centric data: 8 (+0)
Overall activity RevMan Web vs. RevMan 5 (2 years)
Sprint started
Completed:
Story | Objective/Epic | Release | Demo |
---|---|---|---|
Paste study characteristics from the clipboard | Improve transfer of data into RMW | Yes | Yes |
Import study data from file (not yet completed) | Improve transfer of data into RMW | No | Yes |
Expected format for tabular data | Improve transfer of data into RMW | - | Yes |
Other work completed:
- End-2-End automatic tests
- 5 bugs fixed
Activity panel last 30 days
Reviews with advanced features (only use RevMan Web)
- In total: 261 (+1)
- GRADEPro integration: 182 (+3)
- RoB 2: 136 (+0)
- Study-centric data: 8 (+0)
Overall activity RevMan Web vs. RevMan 5 (2 years)
Sprint started
Completed:
Story | Objective/Epic | Release | Demo |
---|---|---|---|
Add option to edit SoF managed by GRADEpro without updating the analysis data | 21/4 | Yes | |
Find and replace moves to the next editor with a hit | Retire RevMan 5: Find and replace | 5/5 | Yes |
Download forest plots for analyses | Retire RevMan 5: Non-Cochrane reviews | 21/4 | Yes |
Other work completed:
Export of study data to generate test data for import stories
Remove dependency on Archie's JATS conversion service
Activity panel last 30 days
Reviews with advanced features (only use RevMan Web)
- In total: 260 (+6)
- GRADEPro integration: 179 (+4)
- RoB 2: 136 (+5)
- Study-centric data: 8 (+0)